Drawings

Drawings which form part of the Contract are included in the Volume - II of the Contract Documents.

1.7 Record Drawings

Within 28 days of the issue of a Certificate of Completion, the Contractor shall provide Record Drawings in black line on transparent film and in AutoCAD format in CD. These Drawings shall include:

(a) General arrangement drawings of the Permanent Works.
(b) Project Components drawings showing equipment installation, piping and pumping machinery shall be drawn to a horizontal scale of 1:1250 or 1:500 and vertical 1:200 or 1:100.

The Title Block shall be that of the Engineer responsible for the supervision.

The Employer will supply one velograph copy of the issued drawings, which the Contractor may use to prepare the Record Drawings.

1.8 Site Working Hours

The Site shall observe the following Working hours:

Monday to Saturday: 7:30 am to 5:30 pm.

The Contractor shall not increase the Working hours without the prior approval of the Engineer.

1.9 Programme

Before commencing the Works the Contractor shall, in accordance with the relevant clause of the Conditions of Contract, submit to the Engineer for his approval a programme showing the order in which he proposes to carry out the Works. The programme shall be in the form of a bar chart, or any other form as may be agreed by the Engineer, and shall clearly indicate the followings: